英语翻译Standards:1.Mold base steel will be #3 .2.Parting line l

英语翻译
Standards:
1.Mold base steel will be #3 .
2.Parting line locks required on all molds.
3.All ejector assemblies must have rails between the ejector back-up plate and the inside surface of the ejector housing.Stop buttons are not acceptable.
4.All cores and cavities must be stamped with steel type and Rc hardness.
5.All waterlines and airlines to be counter bored and identified (in out air).
7.All ejector plates must be guided,be threaded for press pull back,and be spring loaded.
8.All molds with cams must have positive return and limit switches,& Burger Engineering “Thinswitch” or equivalent micro-switches must be installed in K.O.plate.
9.All molds must have “Progressive Components” CounterView cat #CVPL or CVIN pocketed on the outside of the mold base.
10.Corners of the mold are to be notched at the parting line for plate separation.
12.Mold must run full automatic,or GTC must be notified of the specific details.
13.Customer Name,Part number,description,number of cavities,and GTC Job # must be stamped on the operator side of the mold in ½” letters.
14.Mold must produce parts that have been approved by GTC.prior to mold shipment.
15.One complete set of reproducible drawings must be sent to GTC upon completion of the mold and prior to the final mold payment.
16.Two sets of preliminary mold design prints must be sent to GTC for approval of the design concept only,prior to mold construction.
17.All drawings,tracings and tooling aids that are necessary for mold construction are the property of GTC and must be retained by the mold maker for a period of 6 months and must be shipped to GTC upon request.
18.Runner turn offs required in all multiple cavity cold runner molds.
19.* Replaceable wear surfaces to be of lamina bronze.E.g.gibs,wear plates,etc.
模胚 DME 单位 IN/LB
钉/司 DME 热咀 DME
弹弓 DME 零件标准 DME
钢材 H13 顶针标准 DME
420 螺丝 UNC
P20 喉牙 NPT
D2 定位圈 ¢4.00"+0.00/-0.01
1040 油咀 MILLER/PARKER
0-1 齿轮 DP
S-7 顶棍孔排位 7",4x16",6x28"
鸭鸭的棍子 1年前 已收到1个回答 举报

命运的车 花朵

共回答了17个问题采纳率:94.1% 举报

1.模子基地钢将是#3 .
2.分开线锁要求在所有模子.
3.所有喷射器汇编必须有路轨在喷射器备用板材和喷射器住房的里面表面之间.停止键不是可接受的.
4.所有核心和洞必须被盖印以钢型和Rc 坚硬.
5.所有水线和航空公司不耐烦和逆被辨认(在在空气之外里) .
7.所有喷射器板材必须被引导,穿线为新闻拉扯,和弹簧支撑.
8.所有模子与凸轮必须有正面回归和限位开关,& 起士汉堡工程学"Thinswitch" 或等效micro-switches 必须被安装在K.O.板材里.
9.所有模子必须有"进步组分" CounterView 猫# CVPL 或CVIN pocketed 在模子基地的外部.
10.模子的角落将被刻凹痕在分开线为板材分离.
12.模子必须跑充分自动,或GTC 必须被通报具体细节.
13.客户名称、零件号码、洞的描述、数字,和GTC 工作# 必须被盖印在模子的操作员边在."信件.
14.模子必须导致被GTC.批准了在模子发货之前的零件.
15.一完全套可再生图画必须被送到GTC 在模子的完成和在最后的模子付款之前.
16.二套初步模子设计印刷品必须寄发到GTC 为设计观念的获得批准唯一,在模子建筑之前.
17.是必要的为模子建筑的所有图画、辨别目标和凿出的装饰援助是GTC 物产,必须由模子制作商保留6 个月的期间,必须运输对GTC 根据需要.
18.赛跑者轮offs 必需在所有多个洞冷的赛跑者里铸造.
19.* 可替换的穿戴浮出水面是lamina 古铜.即凹字楔、穿戴板材,等.